Inside SBA

photograph of the Santa Barbara Airport and the new Terminal construction site by Lynn HoustonPlane side view of SBA's new Airline Terminal during construction on July 29, 2010

Airline Terminal Project - The Santa Barbara Airport, owned and operated by the City of Santa Barbara, is embarking on a new Airline Terminal Project - designed to meet current and future passenger demand, alleviate long lines and overcrowding, and improve operations and efficiency. 
The new terminal complex is expected to be complete in 2012.

Watercolor Illustrations and site plan

Project Timeline

2010  Terminal Building

  • Install water, sewer, power, and communication lines January-February 2010
  • Install pad footings and grade beams February - March 2010
  • Pour slab on grade March - April 2010
  • Erect structural steel April - May 2010
  • Erect/install metal decking, pour concrete on metal deck May - June 2010
  • Set electrical transformer/permanent power to the site June 2010
  • Install interior/exterior metal stud framing June 2010
  • Rough in plumbing and electrical July 2010
  • Install PVC and clay tile roofing August - September 2010
  • Install exterior doors September 2010
  • Install drywall September - October 2010
  • Install baggage handling & TSA fixtures & equipment October - November 2010
  • Install security systems and building finishes November - December 2010
  • Tenant improvements - concessions and airlines November 2010 - January 2011
  • Site work pavement and landscape finishes - January 2011
  • Punch list and LEED flushing January - February 2011

Move into new terminal February - March 2011

2011 Construction Complete

  • New Terminal
  • New Loop Road
  • New Short Term Parking Lot

2012 Relocation & Refurbishment of historic Terminal complete

Project Items Completed     

2007 Terminal Design    

2008 Construction Begins  Ramp Reconstruction Taxiway B Construction

2009 Terminal Building    

  • Short Term Parking relocated May 2009
  • Baggage Claim relocated June 2009
  • Terminal Loop Road relocated June 2009
  • Soil Preparation August - November 2009
  • Site Utilities installation December 2009

 

 

Project Information

Airline Terminal Overview

 

Design Features

 

Construction Photographs

 

2010

June - August 6th

SBA Summer Construction

 

January - May

Structural Steel & Floor Slab Construction

 

2009-2010

Site Preparation & Footing Construction

 

2008-2009

Taxiway B, Ramp Reconstruction

and Loop Road Reconfiguration

 
 

Construction Videos

"Postcards of Travel" creation and installation
July 2010

 

Construction Tour with Project Engineer Leif Reynolds
June 2010
 

Steel Structure

April, 2010 
 

Lantern Restoration

April, 2010

 

Batter Boards and Footings  

January 2010

 

Soil Stabilization   

December 2009

What to Expect     

November 2009

 
 

Airline Terminal Newsletter

 

Airline Terminal Newsletter

 

Groundbreaking

Terminal Groundbreaking Event - Video

 

Event - Photographs